Nyamata Water Supply Extension Handed Over

The extended network brings piped water to roughly 6,400 residents across four cells in Bugesera District.

The Nyamata Water Supply Extension was formally handed over to Bugesera District this month, completing eleven months of work.

The project added 18 km of distribution mains, a 250 cubic metre reservoir and 12 public tap stands. Pressure testing and disinfection were completed ahead of commissioning, and district technicians received training on operating and maintaining the network.